Castner Kellner Plant

Provision of Full Project Lifecycle Project Management Services, for a Portfolio of critical enabling projects supporting Project Summer, Including a new site wide Firewater Deluge System, which included 800m of underground pipework installation, an new Pump House and two Deluge Valve Houses.

The portfolio also included:

  • A 500m Chlorine Gas pipeline to delivery Chlorine Gas across the site.

  • Installation of a medium pressure let-down to trains 1 & 2 in the Chlorine Compressor House to raise the delivery pressure of Chlorine gas onsite.

  • Extensive modifications to the Tanker Loading facility to upgrade the capability to allow loading to multiple tankers simultaneously.

  • The destruct and replacement of several large Quench and Distillation vessels.

  • Demolition of an existing storage tank and design, construction and commissioning of a large EDC Storage tank.

  • Design to resize and replace two new Boiler Feed Water Pumps and associated pipework